 Penataan Trotoar di Pulogebang Capai 45 Persen

Sidewalk Arrangement in Pulogebang Has Reached 45 Percent

The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.

It is targeted to be completed by the end of August

East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.

Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games

"It is targeted to be completed by the end of August," he stated, Monday (7/23).

He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night. 

"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told. 

Linked News
Popular News indeks
  1. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye542 personAldi Geri Lumban Tobing
  2. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye520 personFolmer
  3. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye517 personAldi Geri Lumban Tobing
  4. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye517 personNurito
  5. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye508 personBudhi Firmansyah Surapati